News
Students
Parents
Alumni
Faculty And Staff
BAIS Buzz
50 Years
New Campus
Downloads
Wall of Honor  |  Artist Renderings  |  Case Statement  |  Construction Updates Untitled Document
     

First Day of School! - August 19, 2008









Construction - August 07, 2008

Lower level corridor Elementary classroom Final work on another classrom Front office secretary area


Hallway to administration offices Front lobby and
receptionist desk
Paving stone installation outside the front door Paving stone installation
for the parking lot


Front entrance of the campus Security office West side of the campus Completed sports hall construction


East side of the campus as seen from the sports hall Secondary lockers ready for the first day of classes


Construction - July 21, 2008

Front of the new classroom building Final work on computer network cabling Work being done on the sports hall Grass and landscaping outside the building


Construction - July 10, 2008

Completed back stairway Front stairway Completed windows and drainage work Sports hall construction


Construction - June 23, 2008

Piling for Sport Hall Relocation Marble for Library Entrance and installing corridor tiles Electrical Equipment in Power House BAIS Blue Color as Building Trim


Construction - June 4, 2008

Marble installation in lobby Electrical work nearing completion Completed restroom tiling Window installation


Construction - May 26, 2008

Painting classrooms Drainage work Completed drainage ditch Library with tiling complete


Construction - May 9, 2008

Grass installed Tiling work in restrooms   Work on computer network cabling


Construction - May 7, 2008

Light fixtures waiting for installation Classroom windows installed Electrical wiring work Interior door frames and windows installed


Construction - April 29, 2008

Tile on classroom floor   Cabling for computer network  


Construction - April 15, 2008

Ceiling installation   Putting the finishing
touches on windows
Corridor tiling finished


Construction - April 9, 2008

Ceramic tile being installed in the corridor   Cable tray for final
electrical work
Hangers installed for computer network cable system


Construction - April 2, 2008

Looking down the wide corridor on the first level A peek through the door
of a future classroom
A view of the multi-
purpose room from the
back corner
Roof work almost completed


Construction - March 20, 2008



Construction - March 5, 2008



Construction - February 20, 2008



Construction - January 20, 2008



Construction - January 2008



Construction - November 2007



First Piling Driven - October 2007



Cut and Fill - August 2007


Copyright © 2006-2008 Bandung Alliance International School